Luhri Stage-II HEP

Luhri HEP Stage-II is a run of river project on Satluj river near Nanj village, spread over Shimla, Kullu & Mandi districts of Himachal Pradesh. The project is estimated to generate 632 MU of electricity in a 90% dependable year. Investment approval for pre-construction activities of Rs 72.478 Crore was received from GOI on 16.03.18. MoU signed with GoHP on 25.09.2019.

 

The Project shall be financed on 70:30 debt:equity ratio.The estimated cost of the project at March, 2017 price level is Rs. 1182.90 crores.

Sr. No.DescriptionDate
1.Allocation of all three Stages of Luhri Projects to SJVN by GoHP on "Stand Alone Basis”29.08.2017
2.Investment Approval for pre-construction activities from GoI16.03.2018
3.Approval of TOR from MOEF09.04.2018
4.Ist consultation meeting with CEA11.06.2018
5.Award of EIA/EMP studies27.06.2018
6.Submission of application to GoHP for conducting SIA study29.09.2018
7.Submission of application for diversion of forest land08.10.2018
8.Award of SIA report18.07.2019
9.Signing of MoU with GoHP25.09.2019
10.Completion of Drift works30.10.2019