Luhri HEP Stage-II is a run of river project on Satluj river near Nanj village, spread over Shimla, Kullu & Mandi districts of Himachal Pradesh. The project is estimated to generate 632 MU of electricity in a 90% dependable year. Investment approval for pre-construction activities of Rs 72.478 Crore was received from GOI on 16.03.18. MoU signed with GoHP on 25.09.2019.
The Project shall be financed on 70:30 debt:equity ratio.The estimated cost of the project at March, 2017 price level is Rs. 1182.90 crores.
| Sr. No. | Description | Date |
| 1. | Allocation of all three Stages of Luhri Projects to SJVN by GoHP on "Stand Alone Basis” | 29.08.2017 |
| 2. | Investment Approval for pre-construction activities from GoI | 16.03.2018 |
| 3. | Approval of TOR from MOEF | 09.04.2018 |
| 4. | Ist consultation meeting with CEA | 11.06.2018 |
| 5. | Award of EIA/EMP studies | 27.06.2018 |
| 6. | Submission of application to GoHP for conducting SIA study | 29.09.2018 |
| 7. | Submission of application for diversion of forest land | 08.10.2018 |
| 8. | Award of SIA report | 18.07.2019 |
| 9. | Signing of MoU with GoHP | 25.09.2019 |
| 10. | Completion of Drift works | 30.10.2019 |