220 kV Single Zebra, Double Circuit Transmission Line (37 Km) from Switchyard to 220kV HPPTCL network in Snail has been constructed for evacuation of power from 60 MW Naitwar Mori HPS. Work was awarded to M/s KEC International Ltd. on 30.04.2021. Transmission line has been commissioned on 20.10.2023 and is under operation.