Project was bagged by SJVN through tariff-based competitive bidding with a tariff of Rs. 3.11 per kWh on 13.08.2021 from BREDA. The work for 75 MW out of 125 MW was awarded on 08.11.2024. The project has been successfully commissioned and Commercial Operation has been achieved on 05.08.2026.