Beginning from a single hydropower project company, SJVN today has a footprint in a Hydroelectric Projects in Himachal Pradesh, Uttrakhand and in the neighboring countries of Nepal and Bhutan.

SJVN is successfully operating the country’s largest 1500 MW Nathpa Jhakri Hydropower Station and is setting new benchmarks in generation and maintenance year after year, after having tackled the silt erosion problems in under-water turbine parts.

Tandi and Rashil HEPs located on river Chenab in Himachal Pradesh with proposed capacity of 104 MW and 130 MW respectively were allotted by GoHP on 05.01.2021.

After preliminary investigations, a composite proposal of 268 MW  was submitted to DoE, GoHP for approval on 06.05.2022. Approval by GoHP for combined scheme was granted on 02.07.2022. The project has been registered by CEA for further investigation.

Luhri Hydro Electric Project is located on river Satluj spread over Shimla, Kullu and Mandi districts of Himachal Pradesh. Initially LHEP was contemplated as single stage project and Implementation Agreement with Govt. of Himachal Pradesh was signed on 27.10.2008. Govt. of H.P. in March, 2015 advised SJVN to explore the possibility of executing the LHEP as multi-stage project instead of single stage on account of social and environmental concerns. Accordingly three stages (i.e. Luhri HEP Stage- 1 - 210 MW, Luhri HEP Stage-2 – 172 MW and Sunni Dam HEP- 382 MW) were envisaged to harness the hydel potential of Satluj river between Rampur and Kol Dam Hydro Electric Projects. Govt. of H.P. reallocated all three projects on "Stand Alone Basis" to SJVN on 29.08.2017. MoU signed with GoHP on 25.09.2019.

Luhri HEP Stage-1 is a Run of the River (RoR) scheme with installed capacity of 210 MW, located on river Satluj, near Nirath village spread over Shimla and Kullu Districts of Himachal Pradesh. The project holds potential of generating 758 MU of electric energy in a 90% dependable year. Sanction order for Investment approval issued by MoP, GoI on 20.11.2020.

Name of Component
 

Luhri HEP Stage-I

Location/Type/ Capacity
State/CountryHimachal Pradesh
Installed Capacity210 (2x80+2x25)
Dam
 
TypeConcrete Gravity
Height (From Deepest Foundation level)80.00 m
Pressure shaft/Penstock
NumberMain Unit= 2
Auxillary Unit =2
Dia8.0m (Main) & 5.0m(Auxillary)
Length84.00m (Main) & 98.00m(Auxillary)
Power House
TypeDam Toe Surface
Size122 m (L) x 51 m (w) x 66 m(h)
No./ Capacity of generating unitsMain Unit = 2 x 80 MW
Auxiliary Unit = 2 x 25 MW
Type of Turbine.Kaplan/ 4
Design Head37 m

Tail Race Tunnel/Channel

ShapeOpen Channel
Length/Dia120 m/65 m width

Investment approval of Rs. 1810.56 crores for implementation of project accorded by CCEA, GoI on 04.11.2020. Project shall be financed on 80:20 debt equity ratio. Financial closure achieved on 28.02.2022.
 

Sr. No

Description

Date

1.

Signing of Implementation Agreement for Execution Luhri HEP (Single Stage Project) between SJVN and Govt. of Himachal Pradesh

27.10.2008

2.

Allocation of all three Stages/Projects to SJVN by GoHP on "Stand Alone Basis"

29.08.2017

3.

Investment Approval for pre-construction activities from GoI

08.02.2018

4.

TEC of DPR accorded by CEA

01.05.2018

5.

Stage-1 Forest Clearance

19.09.2018

6.

Submission of case for diversion of forest land to MoEF & CC for final approval

24.12.2018

7

Stage-2 Forest Clearance

28.03.2019

8

Submission of PIB memo for main project works

15.07.2019

9

Approval of estimate for diversion of NH by MoRTH

02.09.2019

10

Signing of MoU with GoHP

25.09.2019

11

Environment Clearance from MoEF&CC

17.03.2020

12

Consent to Establish from State PCB

14.09.2020

13

PIB for Investment approval

16.09.2020

14

CCEA approval   

04.11.2020

15

Issuance of Investment approval by MoP, GoI

20.11.2020

     16
 
Award of EPC package for Civil and HM works
 
          24.11.2020
 

17

Award of EPC package for EM works

16.07.2021

     18Foundation stone of project laid by Hon'ble Prime Minister
 
          27.12.2021

Memorandum of Understanding (MOU) was signed with the Govt. of Nepal for the execution of 900 MW Arun – III HE Project on BOOT basis with a construction period of 5 years from date of financial closure of the project and operation period of 25 years. Project is located on river Arun in the Sankhuwasabha Distt. of Nepal, 657 Km from Kathmandu via Birat Nagar. SJVN Arun-3 Power Development Company Pvt. Ltd (SAPDC) was incorporated & registered on 25.04.13 as a private limited company under the Nepalese Companies Act 2063 duly floated by single shareholder company SJVN Ltd with an aim to plan, promote, organize & execute the Arun-3 Hydro-electric Project. Project Development Agreement (PDA) signed with IBN, GoN on 25.11.14.

 DPR of the Project vetted by CEA on 09.06.14 . The EIA report of the project was approved by Ministry of Science, Technology & Environment, GoN on 12.08.15. CCEA accorded approval for Rs. 5723.72 Crore on 22.02.17. Generation license issued by GoN on 03.05.18.

All project access roads connecting to sites have been completed and major works of project through four main packages are under progress.

Location

Capacity

900 MW

State/ Country

Nepal

Basin

Arun

Project Type

Run of River

Diversion Dam/ Tunnel

Type of Dam

Concrete Gravity Dam

Height of Dam

80 m

Crust Level

808m

Length/ Dia of DT

429 m/ 11 m

No. of Intakes

2

Head Race Tunnel

No. of Adits

4

Length of HRT

11.837 KM

Dia of HRT

9.5 m Circular

Discharge

344.68 Cumecs

Surge Shaft

Type

Restricted Orifice

Height

155 m

Dia

24 m

Pressure Shaft

Type of Pressure Shaft

Steel lined

No. of Pressure Shaft(s)/ Penstocks

2/4

Power House

Type

Underground Cavern

No./ Capacity of generating units

4/ 225 MW

Type of Turbine

Vertical Francis

Gross Head

308 m

Design Head

286.21 m

Tail Race Tunnel

Length

108 m

Diameter

10 m

Energy in 90 % Dependable Year

4018.87 Gwh

The Project  is financed on 70 : 30 debt equity ratio.

S.No.

Description

Date

1.

Signing MoU with GoN

02.03.2008

2.

Completion of Survey & Investigation Work

15.01.2011

3.

Submission of DPR of Project to CEA

31.03.2011

4.

Submission of Transmission line DPR to CEA

05.04.2011

5.

 Completion of Public Hearings

24.02.2013

6.

SJVN Arun-3 Power Development Company Pvt. Ltd. (SAPDC) established & Registered.

25.04.2013

7

Vetting of DPR of Project by CEA

09.06.2014

8

Vetting of Transmission Line by CEA

20.06.2014

9

Signing PDA with GoN

25.11.2014

10

EIA approval by GoN

12.08.2015

11

MoU between SAPDC & DoR

05.01.2016

12

Agreement with DoR

29.05.2016

13

PIB approval

20.09.2016

14

CCEA Approval

22.02.2017

15

LoA of Civil Package-I

22.09.2017

16

LoA of Civil Package-II

19.03.2018

17

LoA of HM Package

11.04.2018

18

LoA of EM Package

30.04.2018

19

LoA of Construction Power (47km, 33kv line)

09.08.2018

20

Construction license for construction power line issued by GoN (for 47 km, 33kv line)

28.11.2018

21

Financial Closure achieved

06.02.2020

22

Completion of heading excavation of Face-1 of HRT

23.02.2020

23

Completion of all Adits of HRT

14.04.2020

24

Surface excavation of surge shaft

05.05.2020

   25

Completion of all Adits of power House

 10.12.2020

26

River Diversion

 01.02.2021

 

 

Naitwar Mori Hydro Power Station with a generation potential of 60 MW is located on River Tons, a major tributary of River Yamuna in Uttarkashi district of  Uttarakhand State in North India. The project is designed as a standalone run of the river project. The entire project is on the right bank of river Tons stretching from Barrage site near village Naitwar and Power house complex near Bainol village. Naitwar Mori Hydro Power Station has the potential to generate 265.5 million units of electricity each year. A Memorandum of Understanding for execution of Naitwar Mori project was signed with the Government of Uttarakhand in November 21, 2005.

Hon’ble Union Minister of Power (Independent Charge) Sh. R K Singh and Hon’ble Chief Minister of Uttarakhand Sh. Trivender Singh Rawat laid the foundation stone of the Project at Mori on 30.03.2018.

All major works in 3 packages completed and both units of the project have been commissioned  as per following details.

Unit No.
 
Date of Synchronization
 
COD
 
Unit #1
 
14.11.2023
 
24.11.2023
 
Unit #2
 
29.11.2023
 
04.12.2023
 

Name of Component

Feature

Diversion Structure

Type

Barrage

Height

18.5 m

Length of barrage at top

50 m

Desilting Tank

Type

One, Twin Chamber

Size (in m)

130 (L) x 25 (W) x 13.5 (H)

Head Race Tunnel

Length

4.33 Km, Modified Horseshoe Type

Diameter

5.6 m (Finished)

Design discharge

73.5 m3/s

No. of Adits

02 nos.

Underground Surge Shaft

Height

57.33 m

Diameter

18 m

Pressure Shaft/ Penstocks

No. of Pressure Shafts

One (bifurcated into 2 branches)

Diameter of Pressure Shaft

4.0 m upto bifurcation, 2.8 m dia. of each branch

Length of pressure shaft

97.5 m upto bifurcation, 29 m length of each branch

Underground Power House

No. of units

02 (30 MW each)

Net design head

90.76 m

Type of turbine

Vertical Francis

Tail Race Tunnel

Shape

Modified Horse Shoe

Size

6.5 m (dia.)

Length

188 m

Tail Race Channel

Shape

Trapezoidal

Size

6.0 m wide at bottom & 17.5 m wide at top x 5.75 m (h)

The Project is financed on 70:30 debt equity ratio.

Sr. No.

Description

Date

1.

Execution Agreement between SJVN & GoUk

21.11.2005

2.

TEC of DPR

02.03.2010

3.

Environment Clearance

16.06 2016

4.

Stage-2 Forest Clearance

05.08. 2016

5.

Order regarding "Consent to Establish"

04.07. 2017

6.

Investment Approval

16.10. 2017

7.

Signing of Lease agreement for the forest land with Forest Deptt., GoUk

01.12. 2017

8.

Award of major Civil Works

05.12. 2017

9.

Foundation Stone of project

30.03.2018

10.

Award of Hydro Mechanical Package

18.04. 2018

11.

Award of Electro Mechanical Package

11.06. 2018

12.

Diversion of River

31.01.2019

13.

Complete HRT Excavation

05.07.2021

14.

Complete Power House Excavation

29.04.2022

15.

Boxing-Up of Unit-1

14.10.2022

16.

Completion of Surge Shaft Lining (i/c Grouting)

04.05.2023

17.

Boxing-Up of Unit-2

22.07.2023

18.

Completion of HRT lining

28.08.2023

19.

Reservoir Filling

16.09.2023

20.

Mechanical Spinning of Unit-1

27.09.2023

21.

Mechanical Spinning of Unit-2

24.10.2023

22.

COD (Unit-1)

24.11.2023

23.

COD (Unit-2)

04.12.2023

For Tariff Petition, please Click Here

For additional information in Tariff Petition of NMHEP filed before Hon'ble CERC, please Click here