Beginning from a single hydropower project company, SJVN today has a footprint in a Hydroelectric Projects in Himachal Pradesh, Uttrakhand and in the neighboring countries of Nepal and Bhutan.
SJVN is successfully operating the country’s largest 1500 MW Nathpa Jhakri Hydropower Station and is setting new benchmarks in generation and maintenance year after year, after having tackled the silt erosion problems in under-water turbine parts.
Tandi and Rashil HEPs located on river Chenab in Himachal Pradesh with proposed capacity of 104 MW and 130 MW respectively were allotted by GoHP on 05.01.2021.
After preliminary investigations, a composite proposal of 268 MW was submitted to DoE, GoHP for approval on 06.05.2022. Approval by GoHP for combined scheme was granted on 02.07.2022. The project has been registered by CEA for further investigation.
- The draft R&R Scheme of LHEP Stage-I in respect of Nirath and Bhadrash
- The draft R&R Scheme in r/o Mohal Naula
- Notification dated 08th March, 2021
- Draft Rehabilitation and Resettlement Scheme
- Preliminary Notification
- Land Details
- Final SIA Expert Group Report LHEP Stage- I
- Preliminary Notification issued by GoHP Deptt of MPP and Power i.r.o LHEP-I
- Notification issued by Principal Secretary (Power) to the Government of Himachal Pradesh.
- APPRAISAL REPORT OF THE EXPERT GROUP CONSTITUTED FOR THE EVALUATION OF THE SIA STUDY
- Annual Compliance Reports i.r.o Luhri HEP-I Forest Clearance for the FY 2024-25
- Six Monthly Compliance Reports of conditions stipulated in the Environment Clearance for period October-2024 to March-2025 in respect of Moin Quarry
- Six Monthly Compliance Report of conditions stipulated in the Environment Clearance for period September 2024 to March 2025
- Six Monthly Compliance Reports of conditions stipulated in the Environment Clearance for period October-2024 to March-2025 in respect of Koel Quarry
- Six Monthly Compliance Report of conditions stipulated in the Environment Clearance for period April- 2024 to September-2024 for Moin Quarry
- Six Monthly Compliance Report of conditions stipulated in the Environment Clearance for period April- 2024 to September-2024 for Koel Quarry
- Six Monthly Compliance Report of conditions stipulated in the Environment Clearance for period October- 2023 to March-2024
- Six Monthly Compliance Report of conditions stipulated in the Environment Clearance for period April- 2023 to September -2023
- Six Monthly Monitoring Report on Compliance to Environment Aspects for the period of October, 2022 to March 2023
- Six Monthly Monitoring Report on Compliance to Environmental Aspects from April, 2022 to September, 2022
- Six Monthly Monitoring Report on Compliance to Environmental Aspects-For period October, 2021 - March, 2022
- Half Yearly Monitoring Report on Compliance to Environmental Aspects for the period from April, 2021 to September, 2021
- Environmental Clearance for Mining of Minerals
- Six Monthly Monitoring Report on Compliance to Environmental Aspects (For period October, 2020 - March, 2021) i.r.o Luhri Stage-I HEP
- Half yearly compliance report from April 2020 to September 2020
- Six Monthly Compliance report for the period of October 2019 to March 2020
- Environment Clearance
- Six Monthly Compliance Reports of conditions stipulated in the Environment Clearance for period April-2025 to September-2025
- Six Monthly Compliance Report of conditions stipulated in the Environment Clearance for period April- 2025 to September-2025 for Koel Quarry
- Six Monthly Compliance Report of conditions stipulated in the Environment Clearance for period October- 2025 to March-2026 i.r.o. Luhri
- Six Monthly Compliance Report of conditions stipulated in the Environment Clearance for period October- 2025 to March-2026 for Koel Quarry
- Six Monthly Compliance Reports of conditions stipulated in the Environment Clearance for period October-2025 to March-2026 in respect of Moin Quarry
Luhri Hydro Electric Project is located on river Satluj spread over Shimla, Kullu and Mandi districts of Himachal Pradesh. Initially LHEP was contemplated as single stage project and Implementation Agreement with Govt. of Himachal Pradesh was signed on 27.10.2008. Govt. of H.P. in March, 2015 advised SJVN to explore the possibility of executing the LHEP as multi-stage project instead of single stage on account of social and environmental concerns. Accordingly three stages (i.e. Luhri HEP Stage- 1 - 210 MW, Luhri HEP Stage-2 – 172 MW and Sunni Dam HEP- 382 MW) were envisaged to harness the hydel potential of Satluj river between Rampur and Kol Dam Hydro Electric Projects. Govt. of H.P. reallocated all three projects on "Stand Alone Basis" to SJVN on 29.08.2017. MoU signed with GoHP on 25.09.2019.
Luhri HEP Stage-1 is a Run of the River (RoR) scheme with installed capacity of 210 MW, located on river Satluj, near Nirath village spread over Shimla and Kullu Districts of Himachal Pradesh. The project holds potential of generating 758 MU of electric energy in a 90% dependable year. Sanction order for Investment approval issued by MoP, GoI on 20.11.2020.
Name of Component | Luhri HEP Stage-I |
| Location/Type/ Capacity | |
| State/Country | Himachal Pradesh |
| Installed Capacity | 210 (2x80+2x25) |
| Dam | |
| Type | Concrete Gravity |
| Height (From Deepest Foundation level) | 80.00 m |
| Pressure shaft/Penstock | |
| Number | Main Unit= 2 Auxillary Unit =2 |
| Dia | 8.0m (Main) & 5.0m(Auxillary) |
| Length | 84.00m (Main) & 98.00m(Auxillary) |
| Power House | |
| Type | Dam Toe Surface |
| Size | 122 m (L) x 51 m (w) x 66 m(h) |
| No./ Capacity of generating units | Main Unit = 2 x 80 MW Auxiliary Unit = 2 x 25 MW |
| Type of Turbine. | Kaplan/ 4 |
| Design Head | 37 m |
Tail Race Tunnel/Channel | |
| Shape | Open Channel |
| Length/Dia | 120 m/65 m width |
Investment approval of Rs. 1810.56 crores for implementation of project accorded by CCEA, GoI on 04.11.2020. Project shall be financed on 80:20 debt equity ratio. Financial closure achieved on 28.02.2022.
Sr. No | Description | Date |
1. | Signing of Implementation Agreement for Execution Luhri HEP (Single Stage Project) between SJVN and Govt. of Himachal Pradesh | 27.10.2008 |
2. | Allocation of all three Stages/Projects to SJVN by GoHP on "Stand Alone Basis" | 29.08.2017 |
3. | Investment Approval for pre-construction activities from GoI | 08.02.2018 |
4. | TEC of DPR accorded by CEA | 01.05.2018 |
5. | Stage-1 Forest Clearance | 19.09.2018 |
6. | Submission of case for diversion of forest land to MoEF & CC for final approval | 24.12.2018 |
7 | Stage-2 Forest Clearance | 28.03.2019 |
8 | Submission of PIB memo for main project works | 15.07.2019 |
9 | Approval of estimate for diversion of NH by MoRTH | 02.09.2019 |
10 | Signing of MoU with GoHP | 25.09.2019 |
11 | Environment Clearance from MoEF&CC | 17.03.2020 |
12 | Consent to Establish from State PCB | 14.09.2020 |
13 | PIB for Investment approval | 16.09.2020 |
14 | CCEA approval | 04.11.2020 |
15 | Issuance of Investment approval by MoP, GoI | 20.11.2020 |
| 16 | Award of EPC package for Civil and HM works | 24.11.2020 |
17 | Award of EPC package for EM works | 16.07.2021 |
| 18 | Foundation stone of project laid by Hon'ble Prime Minister | 27.12.2021 |
Memorandum of Understanding (MOU) was signed with the Govt. of Nepal for the execution of 900 MW Arun – III HE Project on BOOT basis with a construction period of 5 years from date of financial closure of the project and operation period of 25 years. Project is located on river Arun in the Sankhuwasabha Distt. of Nepal, 657 Km from Kathmandu via Birat Nagar. SJVN Arun-3 Power Development Company Pvt. Ltd (SAPDC) was incorporated & registered on 25.04.13 as a private limited company under the Nepalese Companies Act 2063 duly floated by single shareholder company SJVN Ltd with an aim to plan, promote, organize & execute the Arun-3 Hydro-electric Project. Project Development Agreement (PDA) signed with IBN, GoN on 25.11.14.
DPR of the Project vetted by CEA on 09.06.14 . The EIA report of the project was approved by Ministry of Science, Technology & Environment, GoN on 12.08.15. CCEA accorded approval for Rs. 5723.72 Crore on 22.02.17. Generation license issued by GoN on 03.05.18.
All project access roads connecting to sites have been completed and major works of project through four main packages are under progress.
Location | |
Capacity | 900 MW |
State/ Country | Nepal |
Basin | Arun |
Project Type | Run of River |
Diversion Dam/ Tunnel | |
Type of Dam | Concrete Gravity Dam |
Height of Dam | 80 m |
Crust Level | 808m |
Length/ Dia of DT | 429 m/ 11 m |
No. of Intakes | 2 |
Head Race Tunnel | |
No. of Adits | 4 |
Length of HRT | 11.837 KM |
Dia of HRT | 9.5 m Circular |
Discharge | 344.68 Cumecs |
Surge Shaft | |
Type | Restricted Orifice |
Height | 155 m |
Dia | 24 m |
Pressure Shaft | |
Type of Pressure Shaft | Steel lined |
No. of Pressure Shaft(s)/ Penstocks | 2/4 |
Power House | |
Type | Underground Cavern |
No./ Capacity of generating units | 4/ 225 MW |
Type of Turbine | Vertical Francis |
Gross Head | 308 m |
Design Head | 286.21 m |
Tail Race Tunnel | |
Length | 108 m |
Diameter | 10 m |
Energy in 90 % Dependable Year | 4018.87 Gwh |
The Project is financed on 70 : 30 debt equity ratio.
S.No. | Description | Date |
1. | Signing MoU with GoN | 02.03.2008 |
2. | Completion of Survey & Investigation Work | 15.01.2011 |
3. | Submission of DPR of Project to CEA | 31.03.2011 |
4. | Submission of Transmission line DPR to CEA | 05.04.2011 |
5. | Completion of Public Hearings | 24.02.2013 |
6. | SJVN Arun-3 Power Development Company Pvt. Ltd. (SAPDC) established & Registered. | 25.04.2013 |
7 | Vetting of DPR of Project by CEA | 09.06.2014 |
8 | Vetting of Transmission Line by CEA | 20.06.2014 |
9 | Signing PDA with GoN | 25.11.2014 |
10 | EIA approval by GoN | 12.08.2015 |
11 | MoU between SAPDC & DoR | 05.01.2016 |
12 | Agreement with DoR | 29.05.2016 |
13 | PIB approval | 20.09.2016 |
14 | CCEA Approval | 22.02.2017 |
15 | LoA of Civil Package-I | 22.09.2017 |
16 | LoA of Civil Package-II | 19.03.2018 |
17 | LoA of HM Package | 11.04.2018 |
18 | LoA of EM Package | 30.04.2018 |
19 | LoA of Construction Power (47km, 33kv line) | 09.08.2018 |
20 | Construction license for construction power line issued by GoN (for 47 km, 33kv line) | 28.11.2018 |
21 | Financial Closure achieved | 06.02.2020 |
22 | Completion of heading excavation of Face-1 of HRT | 23.02.2020 |
23 | Completion of all Adits of HRT | 14.04.2020 |
24 | Surface excavation of surge shaft | 05.05.2020 |
25 | Completion of all Adits of power House | 10.12.2020 |
26 | River Diversion | 01.02.2021 |
- Six Monthly Compliance Report of conditions stipulated in the Environment Clearance for period April-2025 to September-2025
- Six Monthly Compliance Report of conditions stipulated in the Environment Clearance for period October 2024 to March 2025
- Six Monthly Compliance Report of conditions stipulated in the Environment Clearance for period April- 2024 to September-2024
- Six Monthly Compliance Report of conditions stipulated in the Environment Clearance for period October -2023 to March 2024
- Six Monthly Compliance Report of conditions stipulated in the Environment Clearance for period April- 2023 to September -2023
- Six Monthly Monitoring Report on Compliance to Environment Aspects for the period of October, 2022 to March 2023
- Six Monthly Monitoring Report on Compliance to Environment Aspects for the period of April, 2022 to September 2022
- Half Yearly Compliance Reports of Environment Clearance i.r.o Devta Range mining area from April 2022 to September 2022
- Half Yearly Compliance Reports of Environment Clearance i.r.o Sandra Range mining area from April 2022 to September 2022
- Half yearly compliance reports for the period October 2021 to March 2022 in r/o Sandra Range mining area
- Half yearly compliance reports for the period October 2021 to March 2022 in r/o Devta Range mining area
- Six Monthly Monitoring Report on Compliance to Environmental Aspects for the period from October, 2021 to March, 2022
- Forest Clearance Stage-I of diversion of 4.4222 ha. land for Transmission line in Himachal Pradesh i.r.o. Naitwar Mori HEP, Uttrakhand
- State Govt Order for felling of trees for Transmission line in Uttrakhand i.r.o. NMHEP HEP (60 MW)
- Forest Clearance Stage-II of diversion of 4.4222 ha. land for Transmission line in Himachal Pradesh i.r.o. Naitwar Mori HEP, Uttrakhand
- Forest Clearance Stage - I of Diversion of 112.24 ha. land for Transmission line i.r.o. Naitwar Mori HEP, Uttrakhand
- Half yearly Monitoring Report on Compliance to Environmental Aspects for the period from April, 2021 to September, 2021
- Half yearly compliance reports for the period April 2021 to September 2021 in r/o Sandra Range mining area
- Half yearly compliance reports for the period of April 2021 to September 2021 in r/o Devta Range mining area
- Half yearly compliance report i.r.o. NMHEP from October 2020 to March 2021
- Half yearly compliance report i.r.o. Devta Range mining area from October 2020 to March 2021
- Half yearly compliance report i.r.o. Sandra Range mining area from October 2020 to March 2021
- Half yearly compliance report i.r.o. Sandra Range mining area from April 2020 to September 2020
- Half yearly compliance report i.r.o. Devta Range mining area from April 2020 to September 2020
- Half yearly compliance report from April 2020 to September 2020
- Six-monthly Compliance Report for period of October,2019 to March, 2020.
- Environment Clearance
- Six Monthly Compliance Report of conditions stipulated in the Environment Clearance for period October 2025 to March 2026
Naitwar Mori Hydro Power Station with a generation potential of 60 MW is located on River Tons, a major tributary of River Yamuna in Uttarkashi district of Uttarakhand State in North India. The project is designed as a standalone run of the river project. The entire project is on the right bank of river Tons stretching from Barrage site near village Naitwar and Power house complex near Bainol village. Naitwar Mori Hydro Power Station has the potential to generate 265.5 million units of electricity each year. A Memorandum of Understanding for execution of Naitwar Mori project was signed with the Government of Uttarakhand in November 21, 2005.
Hon’ble Union Minister of Power (Independent Charge) Sh. R K Singh and Hon’ble Chief Minister of Uttarakhand Sh. Trivender Singh Rawat laid the foundation stone of the Project at Mori on 30.03.2018.
All major works in 3 packages completed and both units of the project have been commissioned as per following details.
| Unit No. | Date of Synchronization | COD |
| Unit #1 | 14.11.2023 | 24.11.2023 |
| Unit #2 | 29.11.2023 | 04.12.2023 |
Name of Component | Feature |
Diversion Structure | |
Type | Barrage |
Height | 18.5 m |
Length of barrage at top | 50 m |
Desilting Tank | |
Type | One, Twin Chamber |
Size (in m) | 130 (L) x 25 (W) x 13.5 (H) |
Head Race Tunnel | |
Length | 4.33 Km, Modified Horseshoe Type |
Diameter | 5.6 m (Finished) |
Design discharge | 73.5 m3/s |
No. of Adits | 02 nos. |
Underground Surge Shaft | |
Height | 57.33 m |
Diameter | 18 m |
Pressure Shaft/ Penstocks | |
No. of Pressure Shafts | One (bifurcated into 2 branches) |
Diameter of Pressure Shaft | 4.0 m upto bifurcation, 2.8 m dia. of each branch |
Length of pressure shaft | 97.5 m upto bifurcation, 29 m length of each branch |
Underground Power House | |
No. of units | 02 (30 MW each) |
Net design head | 90.76 m |
Type of turbine | Vertical Francis |
Tail Race Tunnel | |
Shape | Modified Horse Shoe |
Size | 6.5 m (dia.) |
Length | 188 m |
Tail Race Channel | |
Shape | Trapezoidal |
Size | 6.0 m wide at bottom & 17.5 m wide at top x 5.75 m (h) |
The Project is financed on 70:30 debt equity ratio.
Sr. No. | Description | Date |
1. | Execution Agreement between SJVN & GoUk | 21.11.2005 |
2. | TEC of DPR | 02.03.2010 |
3. | Environment Clearance | 16.06 2016 |
4. | Stage-2 Forest Clearance | 05.08. 2016 |
5. | Order regarding "Consent to Establish" | 04.07. 2017 |
6. | Investment Approval | 16.10. 2017 |
7. | Signing of Lease agreement for the forest land with Forest Deptt., GoUk | 01.12. 2017 |
8. | Award of major Civil Works | 05.12. 2017 |
9. | Foundation Stone of project | 30.03.2018 |
10. | Award of Hydro Mechanical Package | 18.04. 2018 |
11. | Award of Electro Mechanical Package | 11.06. 2018 |
12. | Diversion of River | 31.01.2019 |
13. | Complete HRT Excavation | 05.07.2021 |
14. | Complete Power House Excavation | 29.04.2022 |
15. | Boxing-Up of Unit-1 | 14.10.2022 |
16. | Completion of Surge Shaft Lining (i/c Grouting) | 04.05.2023 |
17. | Boxing-Up of Unit-2 | 22.07.2023 |
18. | Completion of HRT lining | 28.08.2023 |
19. | Reservoir Filling | 16.09.2023 |
20. | Mechanical Spinning of Unit-1 | 27.09.2023 |
21. | Mechanical Spinning of Unit-2 | 24.10.2023 |
22. | COD (Unit-1) | 24.11.2023 |
23. | COD (Unit-2) | 04.12.2023 |
For Tariff Petition, please Click Here
For additional information in Tariff Petition of NMHEP filed before Hon'ble CERC, please Click here