SJVN through Open Competitive Bidding conducted by Assam Power Distribution Company Limited (APDCL) bagged 50 MW Solar Power Project on 28.08.2023. PPA was signed with APDCL at tariff of Rs. 3.92 per unit. Work is currently under progress.
Power from Dhaulasidh HEP shall be evacuated through the 220 kV network/substation of HPPTCL. The work for construction of the 220 kV transmission line from the switchyard to the HPPTCL network (17 km) was awarded to M/s KEC International Pvt. Ltd. on 14.06.2022. Stage-I Forest Clearance was accorded by MoEF&CC on 29.05.2025, and approval for execution of work on forest land was granted on 06.10.2025. The signing of agreements for the purchase of private land has been completed. Tower foundation and tower erection works are in progress.
Power from the Luhri Stage-1 HEP shall be evacuated from 400/ 220 kV common pooling station proposed to be constructed at Village Ogli by CTU. Work for construction of 220 kV transmission line (34 km) from switchyard to common pooling station (ISTS network) awarded on 06.07.2022. Forest clearance Stage-1 accorded by MOEF&CC on 27.05.2025 and approval for execution of work in Forest land has been received on 25.02.2026. Signing of agreements for purchase of private land in progress. Foundation work for 1st tower has been completed and further work is in progress.
SJVN has secured a 200 MW Solar Power Project under GUVNL Phase-XXIII at the GSECL Renewable Energy (RE) Park, Khavda, Gujarat. A Power Purchase Agreement (PPA) for the project was signed with GUVNL on 09.07.2024 by SGEL. Works for the entire 200 MW capacity have been awarded to M/s Bridge and Roof Co. (I) Ltd. (100 MW) and M/s Dineshchandra R. Agrawal Infracon Pvt. Ltd. (100 MW).
SJVN has secured a 200 MW Solar Power Project under GUVNL Phase-XXII to be developed in Gujarat. A Power Purchase Agreement (PPA) for the project was signed with GUVNL on 09.04.2024. Grid connectivity has been granted by GETCO on 10.06.2026 while land acquisition is under process. EPC works for 150 MW have been awarded comprising 100 MW to M/s Prozeal Green Energy Ltd. and 50 MW to M/s Oriana Power Ltd.
SJVN has secured a 500 MW Solar Power Project under GUVNL Phase XXI at the GIPCL Renewable Energy (RE) Park, Khavda, Gujarat. A Power Purchase Agreement (PPA) for the project was signed with GUVNL on 09.07.2024. The EPC works for the project have been awarded to Sterling & Wilson (200 MW), KPI Energy Ltd. (200 MW), and Larsen & Toubro (100 MW).
Govt. of Nepal allotted 679 MW Lower Arun Hydro Electric Project in Nepal through competitive bidding on 29.01.2021. The project is situated in the Sankhuwasabha and Bhojpur districts of Eastern Nepal on river Arun downstream of the existing Arun-3 HEP. MoU for the Project was signed with IBN, Govt. of Nepal on 11.07.2021.
The project is envisaged to be operated in tandem operation with Arun-3 HEP. The capacity of the project has been revised to 669 MW with an annual generation of 2901 MU in a 90% dependable year.
Project Development Agreement signed with GoN in the presence of the Hon'ble Prime Minister of India and Hon'ble Prime Minister of Nepal on 01.06.2023.
- Final Social Impact Assessment report for Proposed Additional Private Land Acquisition
- Draft SIA study for the proposed additional land in district Shimla & Mandi
- Issuance of Environment Clearance i.r.o Sunni Dam HEP
- Notification under section 19 (7) in respect of SDHEP, Sunni
- Sunni Dam Notification u/s 11(1) dated 19th January 2021
- Notification dated 16th December, 2020
- Public notice for Public Hearing i.r.o Sunni Dam HEP
- Social Impact Assessment Study for the proposed land acquisition in district Shimla and Mandi
- Notification for Public Hearing
- Social Impact Assessment Unit of Govt. of Himachal Pradesh (HIPA)
- SIA Notification-Right to Fair Compensation & Transparency in Land Acquisition, R&R
- Six Monthly Compliance Report of conditions stipulated in the Environment Clearance for period April-2025 to September-2025
- Six Monthly Compliance Report of conditions stipulated in the Environment Clearance for period October 2024 to March 2025
- Six Monthly Compliance Report of conditions stipulated in the Environment Clearance for period April- 2024 to September-2024
- Six Monthly Compliance Report of conditions stipulated in the Environment Clearance for period October -2023 to March 2024
- Six Monthly Compliance Report of conditions stipulated in the Environment Clearance for period April- 2023 to September -2023
- Six Monthly Monitoring Report on Compliance to Environment Aspects for the period of October, 2022 to March 2023
- Six Monthly Monitoring Report on Compliance to Environmental Aspects for period April, 2022 - September, 2022
- Six Monthly Monitoring Report on Compliance to Environmental Aspects for the period from October, 2021 to March, 2022
- Six Monthly Compliance Report of conditions stipulated in the Environment Clearance for period October -2025 to March 2026
- R&R Scheme of Muhal Talah of District Shimla
- R&R Scheme of Muhal Pandoa of District Shimla
- R&R Scheme of Muhal Ogli of District Shimla
- R&R Scheme of Muhal Malgi of District Shimla
- R&R Scheme of Muhal Majrog of District Shimla
- R&R Scheme of Muhal Lunsu of District Shimla
- R&R Scheme of Muhal Kothi of District Shimla
- R&R Scheme of Muhal Khaira of District Shimla
- R&R Scheme of Muhal Jhunjun of District Shimla
- R&R Scheme of Muhal Jaishi of District Shimla
- R&R Scheme of Muhal Gharena of District Shimla
- R&R Scheme of Muhal Bharara of District Shimla
- R&R Scheme of Muhal Bathora of District Shimla
- R&R Scheme of District Mandi
Sunni Dam HEP is a run of the river type scheme. The project is situated on Satluj river near Khaira village spread over Shimla and Mandi districts of Himachal Pradesh. The project is estimated to generate 1382 MU of electric energy in a 90% dependable year. The project is in the construction stage with the main Civil and HM works Package awarded on 14.01.2023. The EM package was awarded to M/s BHEL on 01.01.2026.
| Name of Component | Sunni Dam Project |
| Location/Type /Capacity | |
| State/country | HP |
| Installed Capacity (MW) | 382 ( 5x73+1 x 17) |
| Dam | |
| Type | Concrete Gravity |
| Height (From deepest foundation level) | 83.00 m |
| Pressure shaft/Penstock | |
| No | 3/6 |
| Length | 190.00 m |
| Power House | |
| Type | Underground |
| No./ Capacity of generating units | 6 units/ (5x 73 + 1 x 17) MW |
| Type of Turbine. | Francis/6 |
| Design Head | 57.85 m |
The Project shall be financed on 70:30 debt equity ratio.The approved cost of the project is Rs. 2614.51 crores at March, 2021 price level.
Sr. No.
Description
Date
1.
Allocation of all three Stages of Luhri project to SJVN by GoHP on "Stand Alone Basis"
29.08.2017
2.
Ist consultation meeting with CEA
17.08.2017
3.
NOC from Wildlife & HPPWD Deptt
06.01.2018 & 21.03.2018
4.
Investment Approval for pre-construction activities from GoI
18.04.2018
5.
Signing of MoU with GoHP
25.09.2019
6.
Recommendation of MoEF&CC for Environment Clearance
07.01.2021
7.
Issuance of Notification under Section -11 by GoHP for private land acquisition
19.01.2021
8.
TEC of DPR
11.02.2021
9.
Submission of PIB to MoP for Investment approval
09.03.2021
10.
Approval of CAT plan from GoHP
01.04.2021
11.
NIT for EPC package for Civil and HM works
20.04.2021
12. Forest Clearance Stage-1 by MoEF&CC 22.12.2021 13. Ground breaking ceremony in presence of Hon'ble Prime Minister 27.12.2021 14. Forest Clearance Stage-2 by MoEF&CC
23.08.2022 15. Sanction Order for Investment approval for Main Civil Works
12.01.2023 16. Award of EPC Package for Main Civil Works & HM Works 14.01.2023 17. River Diversion 13.01.2024 18. Excavation of Adit to PH Crown (191m) 05.08.2024 19. Concrete work for Upstream Coffer Dam 27.05.2025 20. Heading excavation of MAT 25.11.2025 21. Award of EM Package 01.01.2026 22. Double-Lane Steel Truss Bridge 31.01.2026 23. Machine Hall Crown excavation 19.02.2026 24. Dam Excavation upto EL 632m 22.05.2026
- Six Monthly Compliance Report of conditions stipulated in the Environment Clearance for period October 2024 to March 2025
- Six Monthly Compliance Report of conditions stipulated in the Environment Clearance for period April- 2024 to September-2024
- Six Monthly Compliance Report of conditions stipulated in the Environment Clearance for period October-2023 to March -2024
- Six Monthly Compliance Report for the period April- 2023 to September-2023
- Six Monthly Monitoring Report on Compliance to Environment Aspects for the period of October, 2022 to March 2023
- Six Monthly Monitoring Report on Compliance to Environment Aspects for the period of April, 2022 to September 2022
- Six Monthly Monitoring Report on Compliance to Environmental Aspects for the period from October, 2021 to March, 2022
- Six Monthly Monitoring Report on Compliance to Environmental Aspects (For period April, 2021 – September, 2021)
- Six Monthly Monitoring Report on Compliance to Environmental Aspects (For period October, 2020 - March, 2021) i.r.o Dhaulasidh HEP
- Half yearly Compliance report from April 2020 to September 2020
- Six Monthly Compliance report for the period of October 2019 to March 2020
- Request_Form_New
- Environmental Clearance
- Six Monthly Compliance Report of conditions stipulated in the Environment Clearance for period April- 2025 to September-2025
- Six Monthly Compliance Report of conditions stipulated in the Environment Clearance for period October 2025 to March 2026
The Dhaulasidh Hydro Electric Project with capacity of 69.5 MW is located on river Beas, part of the Indus basin, in Hamirpur & Kangra districts of Himachal Pradesh. The project is designed as a Run of the River project with a small live storage that would be utilized for peaking power during the lean season.
The project holds potential of generating 321 million units of electric energy in a 90% dependable year.
Name of Component | Features |
| Diversion Dam | |
| Type | Concrete Gravity Dam |
| Height | 68 m |
| Total length of Dam at top | 205 m |
| Power Intake | 02 nos. Main + 01 no. Auxiliary |
| Diversion Tunnel | |
| Shape | D-shape |
| Diameter | 10.2 m |
| Length | 253 m |
| Penstock | |
| Type | Surface |
| Number | 02 nos. Main + 01 no. Auxiliary |
| Diameter | Main - 4.8 m & Auxiliary - 1.5 m |
| Length of each penstock | Main- 70.8 m each & Auxiliary- 86 m |
| Power House | |
| Type | Dam Toe power house on the Left Bank |
| Units | Main Units- 2 nos. (33 MW each) Auxiliary Unit-1 no. (3.5 MW) |
| Type of Turbine | Vertical Francis |
| Design Discharge | Main Units- 161.34 m3/ sec Auxiliary Unit- 8.67 m3/ sec |
Tail Race Tunnel/Channel | |
| Type | Open Channel |
| Length | Main Units- 51 m Auxiliary Unit- 59 m |
Investment Approval for an estimated cost of Rs. 687.97 crores accorded by GoI on 01.10.2020. The Project shall be financed on 80:20 debt equity ratio. Financial closure achieved on 18.04.2022.
S. No. | Description | Date |
1 | TEC from GoHP | 25.06.2011 |
2 | Stage-I Forest Clearance | 06.03.2012 |
3 | Environment Clearance | 21.02.2013 |
4 | Approval of CAT Plan | 01.10.2013 |
5 | Approval of revised cost estimate by GoHP | 11.05.2018 |
6 | Notification of SIA study issued by GoHP | 08.02.2019 |
7 | Submission of PIB memo to MoP | 18.07.2019 |
8 | Extension of FC-I by MoEF up to 01.11.2020 | 03.09.2019 |
9 | Signing of MoU with GoHP | 25.09.2019 |
10 | Forest Clearance Stage-2 by MoEF&CC | 11.08.2020 |
11 | PIB recommendations for Investment approval | 16.09.2020 |
12 | Investment Approval of project from GoI | 01.10.2020 |
13 | Award of EPC package for Civil and HM works | 06.05.2021 |
14 | Consent to Establish from HP State Pollution Control Board | 06.05.2021 |
| 15 | Foundation stone of project laid by Hon'ble Prime Minister | 27.12.2021 |
| 16 | River Diversion | 15.02.2022 |
| 17 | Completion of Cofferdam | 05.07.2022 |
| 18 | Excavation for all Project Components | 28.03.2023 |
| 19 | Erection of Draft tube liners of both units | 13.05.2024 |
| 20 | Erection of EOT crane in Service Bay | 15.11.2024 |
| 21 | HST of Spiral Case of Unit-1 | 18.07.2026 |
Memorandum of Understanding (MOU) was signed with the Govt. of Nepal for the execution of 900 MW Arun – III HE Project on BOOT basis with a construction period of 5 years from date of financial closure of the project and operation period of 25 years. Project is located on river Arun in the Sankhuwasabha Distt. of Nepal, 657 Km from Kathmandu via Birat Nagar. SJVN Arun-3 Power Development Company Pvt. Ltd (SAPDC) was incorporated & registered on 25.04.13 as a private limited company under the Nepalese Companies Act 2063 duly floated by single shareholder company SJVN Ltd with an aim to plan, promote, organize & execute the Arun-3 Hydro-electric Project. Project Development Agreement (PDA) signed with IBN, GoN on 25.11.14. The major works of project through five main packages are under progress.
Location | |
Capacity | 900 MW |
State/ Country | Nepal |
Basin | Arun |
Project Type | Run of River |
Diversion Dam/ Tunnel | |
Type of Dam | Concrete Gravity Dam |
Height of Dam | 80 m |
Crust Level | 808m |
Length/ Dia of DT | 429 m/ 11 m |
No. of Intakes | 2 |
Head Race Tunnel | |
No. of Adits | 4 |
Length of HRT | 11.837 KM |
Dia of HRT | 9.5 m Circular |
Discharge | 344.68 Cumecs |
Surge Shaft | |
Type | Restricted Orifice |
Height | 155 m |
Dia | 24 m |
Pressure Shaft | |
Type of Pressure Shaft | Steel lined |
No. of Pressure Shaft(s)/ Penstocks | 2/4 |
Power House | |
Type | Underground Cavern |
No./ Capacity of generating units | 4/ 225 MW |
Type of Turbine | Vertical Francis |
Gross Head | 308 m |
Design Head | 286.21 m |
Tail Race Tunnel | |
Length | 108 m |
Diameter | 10 m |
Energy in 90 % Dependable Year | 4018.87 Gwh |
The Project is financed on 70 : 30 debt equity ratio.
S.No. | Description | Date |
1. | Signing MoU with GoN | 02.03.2008 |
2. | Completion of Survey & Investigation Work | 15.01.2011 |
3. | Submission of DPR of Project to CEA | 31.03.2011 |
4. | Submission of Transmission line DPR to CEA | 05.04.2011 |
5. | Completion of Public Hearings | 24.02.2013 |
6. | SJVN Arun-3 Power Development Company Pvt. Ltd. (SAPDC) established & Registered. | 25.04.2013 |
7 | Vetting of DPR of Project by CEA | 09.06.2014 |
8 | Vetting of Transmission Line by CEA | 20.06.2014 |
9 | Signing PDA with GoN | 25.11.2014 |
10 | EIA approval by GoN | 12.08.2015 |
11 | MoU between SAPDC & DoR | 05.01.2016 |
12 | Agreement with DoR | 29.05.2016 |
13 | PIB approval | 20.09.2016 |
14 | CCEA Approval | 22.02.2017 |
15 | LoA of Civil Package-I | 22.09.2017 |
16 | LoA of Civil Package-II | 19.03.2018 |
17 | LoA of HM Package | 11.04.2018 |
18 | LoA of EM Package | 30.04.2018 |
19 | LoA of Construction Power (47km, 33kv line) | 09.08.2018 |
20 | Construction license for construction power line issued by GoN (for 47 km, 33kv line) | 28.11.2018 |
21 | Financial Closure achieved | 06.02.2020 |
22 | Completion of heading excavation of Face-1 of HRT | 23.02.2020 |
23 | Completion of all Adits of HRT | 14.04.2020 |
24 | Surface excavation of surge shaft | 05.05.2020 |
25 | Completion of all Adits of power House | 10.12.2020 |
26 | River Diversion | 01.02.2021 |
| 27 | Powerhouse cavern excavation | 01.08.2021 |
28 | Transformer Hall excavation | 14.10.2021 |
29 | Pressure shafts excavation | 18.02.2024 |
30 | Erection of Intake Gates | 20.09.2024 |
31 | Transformer Hall concreting | 28.10.2024 |
32 | Surge Shaft Lining Work | 23.05.2025 |
33 | HRT Heading | 23.05.2025 |
34 | Unit-1, Unit-2 and Unit-3 Pit-free achieved | 08.12.2025 |
35 | HRT benching | 30.04.2026 |
36 | Erection of Draft Tube Gates | 22.05.2026 |