Under Construction

SJVN through Open Competitive Bidding conducted by Assam Power Distribution Company Limited (APDCL) bagged 50 MW Solar Power Project on 28.08.2023. PPA was signed with APDCL at tariff of Rs. 3.92 per unit. Work is currently under progress.

Power from Dhaulasidh HEP shall be evacuated through the 220 kV network/substation of HPPTCL. The work for construction of the 220 kV transmission line from the switchyard to the HPPTCL network (17 km) was awarded to M/s KEC International Pvt. Ltd. on 14.06.2022. Stage-I Forest Clearance was accorded by MoEF&CC on 29.05.2025, and approval for execution of work on forest land was granted on 06.10.2025. The signing of agreements for the purchase of private land has been completed. Tower foundation and tower erection works are in progress.

Power from the Luhri Stage-1 HEP shall be evacuated from 400/ 220 kV common pooling station proposed to be constructed at Village Ogli by CTU. Work for construction of 220 kV transmission line (34 km) from switchyard to common pooling station (ISTS network) awarded on 06.07.2022. Forest clearance Stage-1 accorded by MOEF&CC on 27.05.2025 and approval for execution of work in Forest land has been received on 25.02.2026. Signing of agreements for purchase of private land in progress. Foundation work for 1st tower has been completed and further work is in progress.

SJVN has secured a 200 MW Solar Power Project under GUVNL Phase-XXIII at the GSECL Renewable Energy (RE) Park, Khavda, Gujarat. A Power Purchase Agreement (PPA) for the project was signed with GUVNL on 09.07.2024 by SGEL. Works for the entire 200 MW capacity have been awarded to M/s Bridge and Roof Co. (I) Ltd. (100 MW) and M/s Dineshchandra R. Agrawal Infracon Pvt. Ltd. (100 MW).

SJVN has secured a 200 MW Solar Power Project under GUVNL Phase-XXII to be developed in Gujarat. A Power Purchase Agreement (PPA) for the project was signed with GUVNL on 09.04.2024. Grid connectivity has been granted by GETCO on 10.06.2026 while land acquisition is under process. EPC works for 150 MW have been awarded comprising 100 MW to M/s Prozeal Green Energy Ltd. and 50 MW to M/s Oriana Power Ltd.

SJVN has secured a 500 MW Solar Power Project under GUVNL Phase XXI at the GIPCL Renewable Energy (RE) Park, Khavda, Gujarat. A Power Purchase Agreement (PPA) for the project was signed with GUVNL on 09.07.2024. The EPC works for the project have been awarded to Sterling & Wilson (200 MW), KPI Energy Ltd. (200 MW), and Larsen & Toubro (100 MW).

Govt. of Nepal allotted 679 MW Lower Arun Hydro Electric Project in Nepal through competitive bidding on 29.01.2021. The project is situated in the Sankhuwasabha and Bhojpur districts of Eastern Nepal on river Arun downstream of the existing Arun-3 HEP.   MoU for the Project was signed with IBN, Govt. of Nepal on 11.07.2021.

The project is envisaged to be operated in tandem operation with Arun-3 HEP. The capacity of the project has been revised to 669 MW with an annual generation of 2901 MU in a 90% dependable year.

Project Development Agreement signed with GoN in the presence of the Hon'ble Prime Minister of India and Hon'ble Prime Minister of Nepal on 01.06.2023. 

Sunni Dam HEP is a run of the river type scheme. The project is situated on Satluj river near Khaira village spread over Shimla and Mandi districts of Himachal Pradesh. The project is estimated to generate 1382 MU of electric energy in a 90% dependable year. The project is in the construction stage with the main Civil and HM works Package awarded on 14.01.2023. The EM package was awarded to M/s BHEL on 01.01.2026. 

Name of ComponentSunni Dam Project
Location/Type /Capacity 
State/countryHP
Installed Capacity (MW)382 ( 5x73+1 x 17)
Dam 
TypeConcrete Gravity
Height (From deepest foundation level)83.00 m
Pressure shaft/Penstock 
No3/6
Length190.00 m
Power House 
TypeUnderground
No./ Capacity of generating units6 units/ (5x 73 + 1 x 17) MW
Type of Turbine.Francis/6
Design Head57.85 m

The Project shall be financed on 70:30 debt equity ratio.The approved cost of the project is Rs. 2614.51 crores at March, 2021 price level.
 

  1. Sr. No.

    Description

    Date

    1.

    Allocation of all three Stages of Luhri project to SJVN by GoHP on "Stand Alone Basis"

    29.08.2017

    2.

    Ist consultation meeting with CEA

    17.08.2017

    3.

    NOC from Wildlife & HPPWD Deptt

    06.01.2018 & 21.03.2018

    4.

    Investment Approval for pre-construction activities from GoI

    18.04.2018

    5.

    Signing of MoU with GoHP

    25.09.2019

    6.

    Recommendation of MoEF&CC for Environment Clearance

    07.01.2021

    7.

    Issuance of Notification under Section -11 by GoHP for private land acquisition

    19.01.2021

    8.

    TEC of DPR

    11.02.2021

    9.

    Submission of PIB to MoP for Investment approval

    09.03.2021

    10.

    Approval of CAT plan from GoHP

    01.04.2021

    11.

    NIT for EPC package for Civil and HM works

    20.04.2021

      12.Forest Clearance Stage-1 by MoEF&CC             22.12.2021
      13.Ground breaking ceremony in presence of Hon'ble Prime Minister             27.12.2021
      14.Forest Clearance Stage-2 by MoEF&CC
     
                 23.08.2022
      15.Sanction Order for Investment approval for Main Civil Works
     
                12.01.2023
      16.Award of EPC Package for Main Civil Works & HM Works            14.01.2023
      17.River Diversion            13.01.2024
      18.Excavation of Adit to PH Crown (191m)           05.08.2024
      19.Concrete work for Upstream Coffer Dam           27.05.2025
      20.Heading excavation of MAT            25.11.2025
      21.Award of EM Package           01.01.2026
      22.Double-Lane Steel Truss Bridge           31.01.2026
      23.Machine Hall Crown excavation          19.02.2026
      24.Dam Excavation upto EL 632m           22.05.2026

     

The Dhaulasidh Hydro Electric Project with capacity of 69.5 MW is located on river Beas, part of the Indus basin, in Hamirpur & Kangra districts of Himachal Pradesh. The project is designed as a Run of the River project with a small live storage that would be utilized for peaking power during the lean season.

The project holds potential of generating 321 million units of electric energy in a 90% dependable year.

Name of Component
 

Features

Diversion Dam
TypeConcrete Gravity Dam
Height68 m
Total length of Dam at top205 m
Power Intake02 nos. Main + 01 no. Auxiliary
Diversion Tunnel
 
ShapeD-shape
Diameter10.2 m
Length253 m
Penstock
TypeSurface
Number02 nos. Main + 01 no. Auxiliary
DiameterMain - 4.8 m & Auxiliary - 1.5 m
Length of each penstockMain- 70.8 m each & Auxiliary- 86 m
Power House
TypeDam Toe power house on the Left Bank
Units

Main Units- 2  nos. (33 MW each)

Auxiliary Unit-1 no. (3.5 MW)

Type of TurbineVertical Francis
Design Discharge

Main Units- 161.34 m3/ sec

Auxiliary Unit- 8.67 m3/ sec

Tail Race Tunnel/Channel

TypeOpen Channel
Length

Main Units- 51 m

Auxiliary Unit- 59 m

Investment Approval for an estimated cost of Rs. 687.97 crores accorded by GoI on 01.10.2020. The Project shall be financed on 80:20 debt equity ratio. Financial closure achieved on 18.04.2022.

S. No.

Description

Date

1

TEC from GoHP

25.06.2011

2

Stage-I Forest Clearance

06.03.2012

3

Environment Clearance

21.02.2013

4

Approval of CAT Plan

01.10.2013

5

Approval of revised cost estimate by GoHP

11.05.2018

6

Notification of SIA study issued by GoHP

08.02.2019

7

Submission of PIB memo to MoP

18.07.2019

8

Extension of FC-I by MoEF up to 01.11.2020

03.09.2019

9

Signing of MoU with GoHP

25.09.2019

10

Forest Clearance Stage-2  by MoEF&CC

11.08.2020

11

PIB recommendations for Investment approval

16.09.2020

12

Investment Approval of project from GoI

01.10.2020

13

Award of EPC package for Civil and HM works

06.05.2021

14

Consent to Establish from HP State Pollution Control Board

06.05.2021

15Foundation stone of project laid by Hon'ble Prime Minister
 

27.12.2021
 

16River Diversion

15.02.2022

17Completion of Cofferdam

05.07.2022

18Excavation for all Project Components

28.03.2023

19Erection of Draft tube liners of both units 

13.05.2024

20Erection of EOT crane in Service Bay 

15.11.2024

21HST of Spiral Case of Unit-1 

18.07.2026

Memorandum of Understanding (MOU) was signed with the Govt. of Nepal for the execution of 900 MW Arun – III HE Project on BOOT basis with a construction period of 5 years from date of financial closure of the project and operation period of 25 years. Project is located on river Arun in the Sankhuwasabha Distt. of Nepal, 657 Km from Kathmandu via Birat Nagar. SJVN Arun-3 Power Development Company Pvt. Ltd (SAPDC) was incorporated & registered on 25.04.13 as a private limited company under the Nepalese Companies Act 2063 duly floated by single shareholder company SJVN Ltd with an aim to plan, promote, organize & execute the Arun-3 Hydro-electric Project. Project Development Agreement (PDA) signed with IBN, GoN on 25.11.14. The major works of project through five main packages are under progress.

Location

Capacity

900 MW

State/ Country

Nepal

Basin

Arun

Project Type

Run of River

Diversion Dam/ Tunnel

Type of Dam

Concrete Gravity Dam

Height of Dam

80 m

Crust Level

808m

Length/ Dia of DT

429 m/ 11 m

No. of Intakes

2

Head Race Tunnel

No. of Adits

4

Length of HRT

11.837 KM

Dia of HRT

9.5 m Circular

Discharge

344.68 Cumecs

Surge Shaft

Type

Restricted Orifice

Height

155 m

Dia

24 m

Pressure Shaft

Type of Pressure Shaft

Steel lined

No. of Pressure Shaft(s)/ Penstocks

2/4

Power House

Type

Underground Cavern

No./ Capacity of generating units

4/ 225 MW

Type of Turbine

Vertical Francis

Gross Head

308 m

Design Head

286.21 m

Tail Race Tunnel

Length

108 m

Diameter

10 m

Energy in 90 % Dependable Year

4018.87 Gwh

The Project  is financed on 70 : 30 debt equity ratio.

S.No.

Description

Date

1.

Signing MoU with GoN

02.03.2008

2.

Completion of Survey & Investigation Work

15.01.2011

3.

Submission of DPR of Project to CEA

31.03.2011

4.

Submission of Transmission line DPR to CEA

05.04.2011

5.

 Completion of Public Hearings

24.02.2013

6.

SJVN Arun-3 Power Development Company Pvt. Ltd. (SAPDC) established & Registered.

25.04.2013

7

Vetting of DPR of Project by CEA

09.06.2014

8

Vetting of Transmission Line by CEA

20.06.2014

9

Signing PDA with GoN

25.11.2014

10

EIA approval by GoN

12.08.2015

11

MoU between SAPDC & DoR

05.01.2016

12

Agreement with DoR

29.05.2016

13

PIB approval

20.09.2016

14

CCEA Approval

22.02.2017

15

LoA of Civil Package-I

22.09.2017

16

LoA of Civil Package-II

19.03.2018

17

LoA of HM Package

11.04.2018

18

LoA of EM Package

30.04.2018

19

LoA of Construction Power (47km, 33kv line)

09.08.2018

20

Construction license for construction power line issued by GoN (for 47 km, 33kv line)

28.11.2018

21

Financial Closure achieved

06.02.2020

22

Completion of heading excavation of Face-1 of HRT

23.02.2020

23

Completion of all Adits of HRT

14.04.2020

24

Surface excavation of surge shaft

05.05.2020

   25

Completion of all Adits of power House

 10.12.2020

26

River Diversion

 01.02.2021

  27

Powerhouse cavern excavation 

                                       01.08.2021

28

Transformer Hall excavation 

14.10.2021

29

Pressure shafts excavation 

18.02.2024

30

Erection of Intake Gates

20.09.2024

31

Transformer Hall concreting

28.10.2024

32

Surge Shaft Lining Work

23.05.2025

33

HRT Heading 

23.05.2025

34

Unit-1, Unit-2 and Unit-3 Pit-free achieved

08.12.2025

35

HRT benching 

30.04.2026

36

Erection of Draft Tube Gates 

22.05.2026