Under Construction

100 MW RUVITL NAWA Solar Power Project was awarded on 06.10.2023 with a tariff of ₹2.62 per unit. EPC contract has been awarded on 21.01.2025. Work is currently under progress.

The project was bagged through tariff-based competitive bidding process at Rs. 2.88 per unit conducted by GUVNL PPA was signed on 23.04.2021. Work is currently under progress.

The project was bagged by SJVN through open competitive bidding with a tariff of Rs. 2.21 per unit. The work was awarded on 06.05.2021 and is currently in progress. 

The project was bagged through tariff-based competitive bidding process at Rs. 2.29 per unit conducted by the GUVNL. Work is currently under progress.

The project was bagged through tariff-based competitive bidding process at Rs. 2.29 per unit conducted by the GUVNL. Work is currently under progress.

Luhri Hydro Electric Project is located on river Satluj spread over Shimla, Kullu and Mandi districts of Himachal Pradesh. Initially LHEP was contemplated as single stage project and Implementation Agreement with Govt. of Himachal Pradesh was signed on 27.10.2008. Govt. of H.P. in March, 2015 advised SJVN to explore the possibility of executing the LHEP as multi-stage project instead of single stage on account of social and environmental concerns. Accordingly three stages (i.e. Luhri HEP Stage- 1 - 210 MW, Luhri HEP Stage-2 – 172 MW and Sunni Dam HEP- 382 MW) were envisaged to harness the hydel potential of Satluj river between Rampur and Kol Dam Hydro Electric Projects. Govt. of H.P. reallocated all three projects on "Stand Alone Basis" to SJVN on 29.08.2017. MoU signed with GoHP on 25.09.2019.

Luhri HEP Stage-1 is a Run of the River (RoR) scheme with installed capacity of 210 MW, located on river Satluj, near Nirath village spread over Shimla and Kullu Districts of Himachal Pradesh. The project holds potential of generating 758 MU of electric energy in a 90% dependable year. Sanction order for Investment approval issued by MoP, GoI on 20.11.2020.

Name of Component
 

Luhri HEP Stage-I

Location/Type/ Capacity
State/CountryHimachal Pradesh
Installed Capacity210 (2x80+2x25)
Dam
 
TypeConcrete Gravity
Height (From Deepest Foundation level)80.00 m
Pressure shaft/Penstock
NumberMain Unit= 2
Auxillary Unit =2
Dia8.0m (Main) & 5.0m(Auxillary)
Length84.00m (Main) & 98.00m(Auxillary)
Power House
TypeDam Toe Surface
Size122 m (L) x 51 m (w) x 66 m(h)
No./ Capacity of generating unitsMain Unit = 2 x 80 MW
Auxiliary Unit = 2 x 25 MW
Type of Turbine.Kaplan/ 4
Design Head37 m

Tail Race Tunnel/Channel

ShapeOpen Channel
Length/Dia120 m/65 m width

Investment approval of Rs. 1810.56 crores for implementation of project accorded by CCEA, GoI on 04.11.2020. Project shall be financed on 80:20 debt equity ratio. Financial closure achieved on 28.02.2022.
 

Sr. No

Description

Date

1.

Signing of Implementation Agreement for Execution Luhri HEP (Single Stage Project) between SJVN and Govt. of Himachal Pradesh

27.10.2008

2.

Allocation of all three Stages/Projects to SJVN by GoHP on "Stand Alone Basis"

29.08.2017

3.

Investment Approval for pre-construction activities from GoI

08.02.2018

4.

TEC of DPR accorded by CEA

01.05.2018

5.

Stage-1 Forest Clearance

19.09.2018

6.

Submission of case for diversion of forest land to MoEF & CC for final approval

24.12.2018

7

Stage-2 Forest Clearance

28.03.2019

8

Submission of PIB memo for main project works

15.07.2019

9

Approval of estimate for diversion of NH by MoRTH

02.09.2019

10

Signing of MoU with GoHP

25.09.2019

11

Environment Clearance from MoEF&CC

17.03.2020

12

Consent to Establish from State PCB

14.09.2020

13

PIB for Investment approval

16.09.2020

14

CCEA approval   

04.11.2020

15

Issuance of Investment approval by MoP, GoI

20.11.2020

16

Award of EPC package for Civil and HM works  

24.11.2020

17

Award of EPC package for EM works

16.07.2021

  18Foundation stone of project laid by Hon'ble Prime Minister  27.12.2021

19

River diversion25.06.2022

Power Evacuation system consists of 277 km long 400 kv DC Transmission line from Diding (Project Area) in Nepal through Dhalkebar (Nepal border) to Sitamarhi (India). Out of this, the Nepal portion of 217 km from Arun-3 Power House (Diding) to Nepal Border (Bathnaha) is being constructed by SJVN. DPR for this 217 km Transmission Line amounting to Rs. 1236.13 crores approved by CEA on 07.02.18 at PL of June 2017. Transmission License issued by GoN on 12.02.2019. CCEA accorded investment approval on 08.03.2019.

MoU signed with PGCIL on 28.05.18 for Project Management Consultancy (PMC) for execution of transmission line through 5 packages. All five Packages have been awarded and work is under progress.

S.No.

Description

Date

1.

Approval of  DPR by CEA

07.02.2018

2

MoU with PGCIL

28.05.2018

3

Transmission License issued by GoN

12.02.2019

4

Investment approval by CCEA

08.03.2019

5

Award of tower packages

08.12.2019

6

Award of Substation package

31.08.2020

7

Award of Conductor Packages

23.12.2020